Missouri City, TX, USA
Case Study Summary:

Park 8Ninety is a 127-acre business park in Missouri City, Texas, just southwest of Houston. Ultimately, 1.8 million square feet of warehouse and flex space is planned, beginning with a speculatively built first phase of 439,704 square feet in three buildings with high ceilings and wide column spacing. Existing tenants include distributors and manufacturers, many serving nearby hospitals or the building trades. The infill site has excellent highway access but had been overlooked because it was entangled by multiple utility easements that made drainage difficult. The municipality of Missouri City worked with developer Trammell Crow to implement an off-site stormwater detention strategy that raised the site’s elevation and created a new recreational lake at an adjacent city park.

View Full Case Study  Arrow

Case Study Summary: Park 8Ninety is a 127-acre business park in Missouri City, Texas, just southwest of Houston. Ultimately, 1.8 million square feet of warehouse and flex space is planned, beginning with a speculatively built first phase of 439,704 square feet in three buildings with high ceilings and wide column spacing. Existing tenants include distributors and manufacturers, many serving nearby hospitals or the building trades. The infill site has excellent highway access but had been overlooked because it was entangled by multiple utility easements that made drainage difficult. The municipality of Missouri City worked with developer Trammell Crow to implement an off-site stormwater detention strategy that raised the site’s elevation and created a new recreational lake at an adjacent city park.

View Full Case Study  Arrow

LAND USES

  • Industrial
  • Lake
  • Warehouse

SPECIAL FEATURES

  • Distribution warehouse
  • Flex Industrial
  • Multiuse business park
  • Public-private partnership
  • Stormwater retention
  • Suburban infill
PROJECT OVERVIEW
Date Started: 2018
Date Opened: 2018
Metro Area: Houston
Location Type: Inner Suburban
Site Size: 127 Acres / 51.40 Hectares
Project Type: Industrial Facility/Park
RELATED
Webinar

ULI Charlotte - What's Happening Around the Region 2025

This fast-paced webinar offered a spotlight on key business districts in the Charlotte area, with each speaker given 6.5 minutes to present development highlights and local challenges. Featured areas included Uptown Charlotte, South End, South Park, ...

12th and Geneva in Oakdale

In April 2025, the City of Oakdale, Minnesota, engaged ULI Minnesota to convene a Technical Assistance Panel (TAP) to evaluate redevelopment opportunities in a study area centralized around the intersection of 12 and Geneva. This 54-acre area, charac...
Report

Sustainability in Single-Family Rental and Build-to-Rent

The single-family rental sector is rapidly growing, especially in its build-to-rent segment. Learn more about comprehensive sustainability in this sector, including the challenges and opportunities for both environmental and social goals within this ...
Topics
Development